Subject: 19093/Chg Order 2/37C/Citico Pumping Station/T&B Scottdale Contr. Date: Mon, 12 Feb 1990 11:19:00 -0500 RESOLUTION NO. 19093 A RESOLUTION AUTHORIZING CHANGE ORDER NO. 2, CONTRACT 37C, CITICO PUMPING STATION, WITH T&B SCOTTDALE CONTRACTORS, INC., TO INCREASE THE CONTRACT IN THE AMOUNT OF SEVEN THOUSAND, TWO HUNDRED EIGHTY-TWO AND NO/100 DOLLARS ($7,282.00) FOR A TOTAL CONTRACT AMOUNT OF THREE MILLION, SEVEN HUNDRED THIRTY-THREE THOUSAND, EIGHT HUNDRED EIGHTY-SIX AND NO/100 DOLLARS ($3,733,886.00) AND TO INCREASE THE CONTRACT TIME BY EIGHTEEN (18) CALENDAR DAYS CHANGING THE COMPLETION DATE TO JUNE 3, 1991. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA, TENNESSEE, That there be and is hereby authorized Change Order No. 2, Contract 37C, Citico Pumping Station, with T&B Scottdale Contractors, Inc., to increase the contract in the amount of $7,282.00 for a total contract amount of $3,733,886.00, and to increase the contract time by 18 calendar days changing the completion date to June 3, 1991. ADOPTED: July 16, 1991 :cjc